Faulder Water request for proposal issued

A request for proposal for work on the Faulder water system has been issued by the RDOS Public Works department.  The milestones in the RFP include:

  • Award of project Tuesday, June 23rd, 2015
  • Predesign completion including estimate and draft tender – July 22, 2015
  • Final design and tendering of selected work – July 28th, 2015
  • Tender Closing – August 17th, 2015
  • Award of Tender – August 20th, 2015
  • Arrival of Uranium Treatment System – September 21st, 2015
  • Construction Completion – November 6th, 2015
  • Wellhead protection plan and water conservation plan for the Faulder Water System completion – November 6th, 2015