As you may know, we have encountered some problems with the power in Faulder and the new well and treatment system remain off-line as of early November, 2016.

Although the RDOS and contractor were aware of the low quality power at the pump house site and efforts were made to design around it, a tricky harmonic apparently emerged.  A couple of things:

  1. This is up to the vendor and its subcontractors to resolve.  There is no cost to Faulder residents. It is warranty work.
  2. Our vendors are qualified and experienced and are doing their best to track down the power gremlins.  The underlying problem is poor power infrastructure and a lack of interest by BC Hydro in making major upgrades to service a small number of residents.
  3. Hopefully this will be resolved by the end of the month.

 

Plain text

  • No HTML tags allowed.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Lines and paragraphs break automatically.
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions. Registered users of this site do not have to do this.